• Client: Weston County School District
  • Architect: Dale Buckingham Architects LLC
  • Location: Newcastle, Wyoming
  • Completion Date: 2010
  • Delivery Method: General Contractor
Following the fire that burned down the existing building, Hladky Construction built:

  • New Pre-Engineered Steel Transportation Building (16,458 sq. ft. of this building includes offices, conference room, office services rooms, 8 maintenance bays, wash bay, spray paint enclosure, tire maintenance bay, and lube service bay)
  • New Wood-Framed Distribution Building (6,186 sq. ft. of this building includes offices, conference room, office services rooms, document long-term storage, receiving bay, shop with welding bay, and walk-in food storage coolers)
  • Exterior parking for visitors at each building
  • Fenced, key-code access parking for staff and 30 school busses
  • Fueling station